Engineering · Service contract
Mödlingbach steel bridge replacement and abutments
Replacement of the existing Mödlingbach bridge on the Wiener Lokalbahnen with two new steel superstructures and abutments at kilometre 13.072, including demolition planning, general and detailed design, steel structure and abutment planning, assembly…
- Deadline
- Closed 39 days ago
- Location
- Wiener Neudorf, Lower Austria, Austria
About the project
Replacement of the existing Mödlingbach bridge on the Wiener Lokalbahnen with two new steel superstructures and abutments at kilometre 13.072, including demolition planning, general and detailed design, steel structure and abutment planning, assembly planning, tendering, documentation for regulatory procedures, safety and health plan, and project management under the Austrian Construction Coordination Act (BauKG).
Scope of work
Design services for the replacement of the Mödlingbach bridge, including demolition planning, general and detailed design of steel superstructures and abutments, assembly planning, tendering, regulatory documentation, safety and health plan, and project management under the Austrian Construction Coordination Act (BauKG).
Deliverables
- general design (Genereller Entwurf)
- detailed design (Detailentwurf)
- demolition and dismantling planning
- steel superstructure design
- abutment design
- assembly planning
- tender documents for construction
- documentation for regulatory procedures (Materienverfahren)
- safety and health plan (SiGe-Plan)
- project management and coordination under BauKG
Required services
- structural engineering
- bridge design
- steel construction planning
- demolition planning
- tendering support
- regulatory compliance documentation
- safety and health coordination
- project management
Pelenoir assessment
This project is primarily an engineering and technical planning assignment for the replacement of a railway bridge, focusing on the design and structural planning of steel superstructures and abutments. Secondary scope includes project management and coordination tasks under Austrian regulations.
-
Engineering 80%
Structural and technical engineering for the new steel bridge superstructures, abutments, and associated infrastructure, including detailed design, steel construction planning, assembly planning, and regulatory compliance documentation.
-
Project management and coordination under the Austrian Construction Coordination Act (BauKG), including safety and health planning (SiGe-Plan), tendering support, and regulatory procedure documentation.
How to take part
Who can apply
- compliance with Austrian procurement law (Bundesvergabegesetz 2018)
- eligibility criteria specified in tender documents
What to submit
- offers in German
- electronic submission required
Source
Published on Austrian Public Procurement Search. Original title: WLB-6310005826; Errichtung einer neuen Stahlbrücke mitsamt Widerlagern über den Mödlingbach km 13,078 - Planungsleistungen.
Summary and assessment prepared by Pelenoir from the public notice (14 Oct 2026). The original notice and its documents are binding. Page updated 13 Oct 2026.
Pelenoir PAL
Find the tenders that fit your practice.
PAL reads every public notice and ranks the opportunities that match your portfolio, team and ambitions.