About the project

Engineering and design services for Phase 1 of the Flora Campus Westland development, including a parking garage, vocational school (ISW Vakcollege+), sports hall, social building, and residential tower. The project involves collaboration in a construction team (bouwteam) to advise on the Definitive Design based on an established Preliminary Design, with subsequent agreement on price for execution.

Scope of work

The tender seeks a construction team partner to advise on the Definitive Design phase based on a Preliminary Design for Phase 1 of Flora Campus Westland. The scope includes engineering and design services for a parking garage, vocational school, sports hall, social building, and residential tower. The contract will proceed to execution upon agreement on price.

Deliverables

  • Definitive Design for parking garage, vocational school, sports hall, social building, and residential tower
  • Advice on engineering and technical design
  • Plan of Approach (Plan van Aanpak)
  • Price agreement for execution phase

Required services

  • Engineering services
  • Architectural design (Maken van bouwkundige ontwerpen)
  • Technical design services

Pelenoir assessment

The Flora Campus Westland Phase 1 project primarily involves architectural design and engineering services for a mixed-use development, including a parking garage, vocational school, sports hall, social building, and residential tower. The scope requires refinement of a Preliminary Design into a Definitive Design, with additional focus on construction team coordination and technical planning. The project is classified under multiple AEC business groups due to its multidisciplinary design and engineering requirements.

  • Architectural design and concept development for the parking garage, vocational school, sports hall, social building, and residential tower, including refinement of the Preliminary Design into the Definitive Design.

  • Structural, civil, and technical engineering for the parking garage, vocational school, sports hall, social building, and residential tower, including infrastructure and building services integration.

  • Coordination and management of the construction team (bouwteam) process, including advice on design development, cost estimation, and preparation for the execution phase.

How to take part

Who can apply

  • Open to market parties with relevant expertise in construction and design
  • Electronic submission required via TenderNed
  • Submission in Dutch

What to submit

  • Plan of Approach (Plan van Aanpak)
  • Uniform European Procurement Document (UEA)
  • Electronic submission via TenderNed

Award criteria

  • Price (45% weight)
  • Quality - Plan of Approach (45% weight)
  • Quality - Environment and biodiversity (10% weight)

Tender documents

The visible document package includes PDFs and ZIP files likely containing procurement documents, design briefs, and clarifications. The PDFs named 'Beschrijvend document UAV-GC E Voorzieningen cluster 1 def' and 'Uniform Europees Aanbestedingsdocument (UEA)' probably outline the contract conditions and procurement requirements. ZIP files such as 'Bijlage 4 - 11.zip' and 'Bijlage 18.zip' may contain detailed plans, drawings, or technical specifications for the parking garage, school, sports hall, and residential tower. DOCX files like 'Prijzenblad Bouwteamfase' suggest pricing templates or financial schedules. The exact contents of the ZIP files remain uncertain without access, but their names indicate they likely hold design and construction documentation.

Images from the tender documents

Source

Published on TenderNed. Original title: EUOA UAV-GC E ‘VOORZIENINGEN CLUSTER FASE 1 FLORA CAMPUS WESTLAND IN BOUWTEAM’.