About the project

Preparation of full design documentation, including conceptual, building, and execution designs for the redevelopment of Wygodna Street in Kaputy and a section of Kapucka Street with its intersection with Sochaczewska Street. The project includes obtaining all necessary permits, administrative decisions, and technical conditions for road construction, utilities (sanitary sewer, telecommunications, energy, and others), and ensuring accessibility for disabled persons.

Scope of work

Preparation of design documentation for the redevelopment of Wygodna Street in Kaputy and a section of Kapucka Street with its intersection with Sochaczewska Street, including conceptual, building, and execution designs across multiple disciplines (road, sanitary sewer, energy, telecommunications, etc.). The scope includes obtaining all necessary permits, administrative decisions, technical conditions, and ensuring accessibility for disabled persons. The contractor must also provide cost estimates, bills of quantities, and author supervision during construction.

Deliverables

  • conceptual design
  • building and execution designs for all required disciplines (road, sanitary sewer, energy, telecommunications, etc.)
  • site development plans
  • bill of quantities and cost estimates
  • Specifications for Execution and Acceptance of Works (STWiORB)
  • traffic organization projects (permanent and temporary)
  • applications for administrative decisions (e.g., road investment permit, building permit, or construction notification)
  • sanitary sewer network design for Wygodna Street with connection to Kapucka Street
  • required technical conditions, opinions, agreements, permits, and administrative decisions (including tree felling permits)
  • documentation for obtaining administrative decisions and construction permits
  • geotechnical studies, surveys, and inventories
  • author supervision during construction

Required services

  • engineering design services (road, sanitary sewer, energy, telecommunications, and other utilities)
  • preparation of cost estimates and bills of quantities
  • obtaining administrative permits and decisions
  • author supervision during construction

Pelenoir assessment

The project primarily involves engineering and technical planning for the redevelopment of urban roads and utility networks, including structural, civil, and infrastructure engineering. Secondary aspects include urban design and planning for traffic organization and accessibility, as well as project and construction management for permit acquisition and author supervision.

  • Design of road infrastructure, utility networks (sanitary sewer, telecommunications, energy), structural and technical engineering for the redevelopment of Wygodna and Kapucka Streets, including intersection with Sochaczewska Street. Preparation of geotechnical studies, surveys, and technical conditions for construction.

  • Urban design and spatial planning for the redevelopment of the street network, including traffic organization (permanent and temporary), accessibility for disabled persons, and integration of public infrastructure within the urban context.

  • Obtaining administrative permits and decisions, coordinating author supervision during construction, and ensuring compliance with technical and legal requirements for the project.

How to take part

Who can apply

  • Contractor must demonstrate financial capacity of at least 30,000 PLN
  • Contractor must have completed at least 3 similar design projects for road/utility construction in the last 3 years, each resulting in a final administrative decision (e.g., road investment permit, building permit, or accepted construction notification)
  • Contractor must assign at least one coordinator with unlimited road engineering design qualifications and 3+ years of experience, including 2 completed road/utility design projects
  • Contractor must assign designers with unlimited qualifications in telecommunications, sanitary (water, sewage, heating, ventilation, gas), and electrical/electroenergetic installations, each with 3+ years of experience
  • Contractors may combine roles if one person holds multiple qualifications
  • Consortium members must meet eligibility requirements collectively or individually (no summing of experience)

What to submit

  • Offer submitted electronically via the e-Zamówienia Platform
  • Documents in Polish
  • Warranty deposit of 5,000 PLN
  • List of personnel assigned to the project with their qualifications and experience
  • Evidence of financial capacity (e.g., bank statement or creditworthiness confirmation)
  • References or documents confirming completion of at least 3 similar design projects
  • Power of attorney for representation (if applicable)
  • Statement on cybersecurity requirements (Załącznik nr 6)
  • Declaration of compliance with eligibility criteria and absence of exclusion grounds

Award criteria

  • Price (60% weight)
  • Additional experience of the person assigned to the project (40% weight)

Tender documents

The visible document package includes two files: a PDF titled 'ID postępowania oraz adres strony e-Zamówienia' likely containing procedural identifiers and access details for the e-Zamówienia platform, and a ZIP archive titled 'SWZ i załączniki' (Specification of Contract Conditions and attachments). The ZIP file probably contains the full tender documentation, including the detailed scope of work, technical requirements, submission forms, and templates for offers. Based on the tender context, it likely includes maps, design guidelines, administrative forms, and possibly sample contracts. However, the exact contents of the ZIP file cannot be confirmed without downloading, and no specific file sizes or detailed breakdowns are provided in the source.

Source

Published on e-Zamowienia. Original title: Przygotowanie dokumentacji projektowej ulicy Wygodnej w Kaputach oraz odcinka ulicy Kapuckiej wraz ze skrzyżowaniem z ulicą Sochaczewską.

Summary and assessment prepared by Pelenoir from the public notice (13 Oct 2026). The original notice and its documents are binding. Page updated 12 Oct 2026.