About the project

Supervision of construction works for the energy modernisation of an existing aquatic park, including review of design documentation, participation in procurement for construction works, and investor supervision during execution and warranty periods.

Scope of work

Supervision of construction works for the energy modernisation of Hajnówka Aquatic Park, including verification of design documentation, participation in the procurement process for construction works, and investor supervision during execution and warranty periods. The supervision covers heating, ventilation, and electrical systems with a focus on ground-source heat pumps.

Deliverables

  • Review and verification of design and cost documentation
  • Identification and description of proprietary solutions and equivalent alternatives
  • Verification of norms, technical specifications, and reference documents
  • Written reports on identified errors or inconsistencies in documentation
  • Participation in the preparation and conduct of the construction works procurement process
  • Investor supervision from site handover to final acceptance, including warranty and defect liability periods

Required services

Pelenoir assessment

The project involves the energy modernisation of an existing aquatic park, with a primary focus on investor supervision and project management services. This includes oversight of construction works, procurement participation, and documentation review. A secondary but critical component involves technical engineering support, particularly for heating, ventilation, and electrical systems, ensuring compliance with design and technical standards.

  • Investor supervision of construction works, including review of design and cost documentation, participation in procurement for construction works, and oversight during execution and warranty periods for the energy modernisation of the aquatic park.

  • Technical review of design documentation, verification of norms and technical specifications, and advisory on heating, ventilation, and electrical systems, particularly ground-source heat pumps.

How to take part

Who can apply

  • Experience in providing investor supervision for at least two projects involving heating and ventilation systems with ground-source heat pumps (minimum 100 kW total heating capacity) in the last 3 years, each with a minimum value of 1.5 million PLN gross
  • Availability of a sanitary systems inspector with unlimited construction licenses and at least 5 years of experience, including 6 months of supervision for ground-source heat pump projects (minimum 100 kW heating capacity)
  • Availability of an electrical systems inspector with unlimited construction licenses and at least 5 years of experience, including 6 months of supervision for public building projects (minimum 1 million PLN gross value)
  • Availability of a construction inspector with at least limited construction licenses and 5 years of experience

What to submit

  • Offer prepared in Polish
  • Submission via electronic platform (platformazakupowa.pl)
  • List of services performed in the last 3 years (Annex 3 to the Terms of Reference)
  • List of personnel assigned to the project, including qualifications and experience (Annex 4 to the Terms of Reference)
  • Statement on the absence of exclusion grounds (Annex 8 to the Terms of Reference)
  • For consortia: power of attorney and statement on the division of services (Annex 9 to the Terms of Reference)

Award criteria

  • Price (60% weight)
  • Experience of the sanitary systems inspector (40% weight)

Source