About the project

Relocation and redesign of two 170 kV power lines (L5S1 and L5S2) over approximately 1.4 km in Vargfors, Norsjö Municipality, to connect to the new Malånäset main grid station and Vattenfall's new PT80 station. The project includes design services with an option for preparing tender documents for the execution contract.

Scope of work

Design services for the relocation of two 170 kV power lines (L5S1 and L5S2) over approximately 1.4 km, including preparation of construction documents. The contract includes an option for creating tender documents for the execution contract. The work is to be performed on a running account basis against a budget price.

Deliverables

  • Design documentation for power line relocation
  • Construction documents (optional)

Required services

  • Electrical engineering design
  • Technical construction services for power lines
  • Preparation of tender documents for execution contract (optional)

Pelenoir assessment

This project primarily involves the relocation and redesign of high-voltage power lines, requiring detailed electrical and technical engineering planning. A secondary aspect includes the preparation of tender documents for the execution phase, indicating a minor project management component.

  • Electrical engineering design and technical planning for the relocation of two 170 kV power lines, including structural and civil engineering aspects of the infrastructure.

  • Preparation of tender documents for the execution contract (optional) and coordination of the design process against a budget price.

How to take part

What to submit

  • Tender with estimated budget price for main assignment and option
  • Compliance with supplier code of conduct
  • Signed confidentiality agreement

Award criteria

  • Quality

Tender documents

The visible document package includes standard procurement forms and templates, such as a supplier code of conduct, confidentiality agreement templates, and invoicing instructions. The file '14.6 FFU projektering Ledningsflytt Vargfors L5S1L5S2 rev A.pdf' likely contains the main tender documents (FFU) for the design services, including technical specifications and submission requirements. The 'Avtal UH-2026-401' file appears to be a draft contract for the power line relocation project. The 'Skakrav.pdf' and 'Utvärderingsmodell.pdf' files probably outline technical requirements and the evaluation criteria for tender submissions, respectively. The exact content of these files cannot be confirmed without access, as the documents require login.

Source

Published on e-Avrop. Original title: Projektering Ledningsflytt Vargfors L5S1/L5S2.