Preparation of design and cost documentation for the thermal modernization of the Faculty of Electrical Engineering building at West Pomeranian University of Technology. The project includes insulation of walls, roofs, and flat roofs, replacement of windows and doors, modernization of heating and hot water systems, installation of a heat exchanger substation, modernization of lighting, and construction of a telecommunication network for a future BMS system.

Scope of work

Preparation of design and cost documentation for two tasks: (1) thermal insulation of walls, roofs, and flat roofs, and replacement of windows and doors; (2) installation of a heat exchanger substation, modernization of heating and hot water systems, lighting modernization, and construction of a telecommunication network for a future BMS system. The scope includes conservation recommendations, energy audits, compliance with DNSH principles, and authorial supervision.

Deliverables

  • design documentation (building and execution projects)
  • cost estimates
  • conservation recommendations
  • energy audit reports
  • ex-ante audit reports
  • DNSH compliance documentation
  • as-built documentation
  • authorial supervision during construction

Required services

Pelenoir assessment

The project focuses on the thermal modernization of an educational building, primarily involving engineering and technical planning for system upgrades and architectural design for building envelope improvements. Sustainability and building performance tasks support compliance and energy efficiency goals.

  • Design and technical planning for thermal insulation, heating and hot water system modernization, lighting upgrades, and installation of a heat exchanger substation and telecommunication network for a future BMS system.

  • Architectural design for thermal modernization, including insulation of walls, roofs, and flat roofs, as well as replacement of windows and doors, while ensuring compliance with conservation recommendations.

  • Energy audits, DNSH compliance documentation, and ex-ante audit reports to ensure the thermal modernization meets sustainability and energy efficiency standards.

How to take part

Who can apply

  • Minimum two completed architectural design services for building modernization or renovation projects in the last three years, each with a net value of at least PLN 50,000
  • Experience in thermal modernization projects, including insulation, window replacement, and installation modernization
  • Eligibility for consortia with combined experience

What to submit

  • Offer prepared in electronic form using qualified electronic signature or trusted signature
  • Documents in formats compliant with Polish interoperability frameworks
  • Submission via e-Zamówienia platform (maximum 250 MB total file size)
  • Additional documents via email (maximum 100 MB) or platform communication forms (maximum 150 MB per form)
  • Mandatory forms and declarations as specified in SWZ attachments

Award criteria

  • Price (60% weight)
  • Warranty period (20% weight)
  • Amount of contractual penalty (20% weight)

Tender documents

The visible document package includes the main tender specification (SWZ) in PDF format, covering procurement conditions and requirements. Two ZIP archives contain detailed project descriptions and supporting documents for each of the two tasks, likely including technical drawings, conservation recommendations, energy audits, and auxiliary reports. Additional PDFs and DOC files provide contract templates, declaration forms, and service lists required for submission. The exact contents of the ZIP archives cannot be confirmed without download, but their filenames suggest they include plans, audits, and compliance documentation for thermal modernization and installation upgrades.

Source

Published on e-Zamowienia. Original title: Wykonanie dokumentacji projektowej i kosztorysowej do realizacji zadania inwestycyjnego pn. „Termomodernizacja budynku Wydziału Elektrycznego przy ul. Sikorskiego 37 w Szczecinie”..

Summary and assessment prepared by Pelenoir from the public notice (8 Oct 2026). The original notice and its documents are binding. Page updated 5 Oct 2026.