About the project

Revitalization of the Schneiderau hydropower plant, including replacement of two existing above-ground pressure pipelines with an underground pipeline (approx. 1,250 m, DN 1600–1800), and construction of a new powerhouse with associated hydraulic, mechanical, and electrical components. The project aims to extend the technical lifespan of key plant components.

Scope of work

Technical planning for the revitalization of the Schneiderau hydropower plant, including submission planning with an optional extension to tender and execution planning, construction supervision, and post-processing. The scope covers hydraulic, mechanical, and electrical engineering for the new powerhouse and underground pressure pipeline.

Deliverables

  • submission planning (Einreichplanung)
  • optional tender and execution planning
  • construction supervision (Baubegleitung)
  • post-processing documentation

Required services

  • technical planning
  • hydraulic engineering
  • mechanical engineering
  • electrical engineering
  • civil engineering

Pelenoir assessment

The Schneiderau Hydropower Plant Revitalization project is primarily an engineering and technical planning endeavor, focusing on the replacement of pressure pipelines and the construction of a new powerhouse with associated hydraulic, mechanical, and electrical components. A secondary aspect involves construction supervision and documentation, which aligns with project and construction management.

  • Technical planning for the revitalization of the Schneiderau hydropower plant, including hydraulic, mechanical, and electrical engineering for the new powerhouse and underground pressure pipeline, as well as civil engineering for structural components.

  • Construction supervision (Baubegleitung) and post-processing documentation to ensure compliance with planning and execution phases.

How to take part

What to submit

  • electronic submission via provia.at
  • participation application (Teilnahmeantrag)
  • project description
  • planning documents

Award criteria

  • technically and economically most advantageous offer

Tender documents

The visible documents likely include the general terms and conditions of ÖBB-Infrastruktur AG (oebb_AGB_DL_2021_01.pdf). The project description (02_Projektbeschreibung.pdf) probably outlines the hydropower plant revitalization, including technical and spatial requirements. The procurement fundamentals (01_Grundlagen des Vergabeverfahrens_Planer.pdf) may detail the legal and procedural framework for the planning services. The task specification (03_Aufgabenstellung_Planer.pdf) likely defines the scope of work, deliverables, and technical requirements for the planning phase. The participation form (01A_Teilnahmeantrag_Planer.pdf) is presumably required for submitting applications. The exact content of these files cannot be confirmed without access, and no drawings or models are explicitly visible in the file names.

Source

Published on Austrian Public Procurement Search. Original title: KW Schneiderau (Technische Planung) - Revitalisierung KW Schneiderau - Einreichplanung mit OPTION Ausschreibungs- und Ausführungsplanung.