About the project

Preparation of design documentation for the construction of a municipal road including road lighting, drainage, and a pedestrian path connecting Saperów Tczewskich Street to Kilińskiego Street in Nisko. The project covers approximately 890 meters of road design, including necessary permits, utility adjustments, and compliance with accessibility standards.

Scope of work

Preparation of design documentation for a municipal road construction project, including road design, lighting, drainage, pedestrian path, and obtaining necessary permits (ZRID). The scope includes conceptual, building, and execution designs, cost estimates, technical specifications, and author supervision.

Deliverables

  • Conceptual design
  • Building permit design (PB) including site development, architectural, and technical designs
  • Execution design
  • Tender documentation
  • Cost estimates and bills of quantities
  • Technical specifications for execution and acceptance of works (STWiOR)
  • Traffic organization project (if required)
  • BIOZ safety and health protection information
  • Final and legally binding decision on road investment realization (ZRID)
  • Environmental decision and water permit (if required)

Required services

  • Civil engineering design
  • Road design
  • Drainage system design
  • Road lighting design
  • Pedestrian path design
  • Utility adjustments and coordination with network managers
  • Obtaining permits and approvals
  • Cost estimation and budgeting
  • Author supervision

Pelenoir assessment

This project primarily involves engineering and technical planning for the design of a municipal road, including drainage, lighting, and pedestrian infrastructure. Secondary aspects include project management for permits, cost estimation, and supervision, as well as urban design for spatial integration and accessibility compliance.

  • Design of the municipal road, drainage system, road lighting, pedestrian path, utility adjustments, and technical coordination for infrastructure compliance and safety.

  • Preparation of cost estimates, tender documentation, author supervision, and coordination of permits (e.g., ZRID, environmental decision, water permit).

  • Integration of the road design with existing urban infrastructure, accessibility standards, and spatial planning for pedestrian and traffic organization.

How to take part

Who can apply

  • Compliance with Polish Public Procurement Law (art. 108, 109, 125)
  • Submission of required statements and documents (e.g., no grounds for exclusion, meeting participation conditions)
  • Possibility of joint bidding with a designated representative
  • Use of electronic communication via the e-Zamówienia platform

What to submit

  • Offers submitted electronically via the e-Zamówienia platform
  • Documents in Polish
  • Statements confirming no grounds for exclusion (Załącznik nr 2 do SWZ)
  • Statements confirming fulfillment of participation conditions (Załącznik nr 3 do SWZ)
  • Power of attorney for joint bidders (if applicable)
  • Documentation in 5 hard copies and 1 electronic copy (CD with PDF, DOC, DWG, XLS formats)

Award criteria

  • Price (60% weight)
  • Payment terms (40% weight)

Tender documents

The visible document package includes a ZIP file labeled 'SWZ z załącznikami ZP.27.zip,' which likely contains the full tender specifications (SWZ), including contractual conditions, technical requirements, and submission forms. The ZIP may also include graphical attachments such as site plans, road layouts, and drainage designs referenced in the tender. A PDF file named 'Komunikacja-w-postepowaniu-5.1.pdf' appears to outline communication procedures for the procurement process, such as electronic correspondence rules and platform usage. The exact contents of the ZIP file remain unverified, but the filenames suggest a focus on contractual, technical, and procedural documentation.

Source

Published on e-Zamowienia. Original title: Opracowanie dokumentacji projektowej na zadanie Budowa drogi gminnej od ul. Saperów Tczewskich do ul. Kilińskiego wraz z oświetleniem drogowym i odwodnieniem.

Summary and assessment prepared by Pelenoir from the public notice (16 Oct 2026). The original notice and its documents are binding. Page updated 15 Oct 2026.