title: "Renovation of two 1950s bascule bridges in Gouda"
url: "https://pelenoir.com/en/tenders-of-europe/projects/renovation-of-two-1950s-bascule-bridges-in-gouda-19737/"
id: 19737
country: "Netherlands"
city: "Gouda"
region: "South Holland"
client: "Gemeente Gouda"
type: "Works contract"
procedure: "Restricted procedure (Niet-openbaar)"
deadline: "2026-12-18"
status: "open"
days_left: 20
status_as_of: "2026-11-28"
disciplines: ["Engineering","Project and construction management","Construction and contracting"]
source: "TenderNed"
source_url: "https://www.tenderned.nl/aankondigingen/overzicht/449632"
updated: "2026-11-18"
publisher: "Pelenoir – Tenders of Europe"
---

# Renovation of two 1950s bascule bridges in Gouda

> Renovation of the Pottersbrug and Rabatbrug, two movable bascule bridges built around 1957.

**Status (2026-11-28):** 20 days left to apply — deadline 2026-12-18 11:30  
**Location:** Gouda, South Holland, Netherlands  
**Contracting authority:** Gemeente Gouda  
**Opportunity type:** Works contract — Restricted procedure (Niet-openbaar)  
**CPV:** 45221100; 45220000; 45315100; 71322000 Engineering design services for the construction of civil engineering works  

## About the project

Renovation of the Pottersbrug and Rabatbrug, two movable bascule bridges built around 1957. The project includes replacing steel [bridge](https://pelenoir.com/en/tenders-of-europe/typologies/roads-and-bridges/) decks, mechanical and electrical installations, structural reinforcements of the substructure, restoration of civil and structural elements, and integration with the Central Bridge Management system (COB). The work is carried out in a two-phase construction team (bouwteam) process: a design phase followed by a realization phase under a construction team agreement.

## Scope of work

The contract covers the renovation of two movable bascule bridges (Pottersbrug and Rabatbrug) through a two-phase construction team (bouwteam) process. Phase 1 is the design and preparation phase (bouwteamfase), and Phase 2 is the realization phase under the construction team agreement. The scope includes replacing steel bridge decks, mechanical and electrical installations, structural reinforcements, civil and structural repairs, and integration with the Central Bridge Management system (COB). The contractor must participate in the design phase and is intended to execute the realization phase.

### Deliverables

- New steel bridge decks
- Replacement of mechanical installations
- Replacement of electrical and automation installations (E/IA)
- Structural reinforcements of the substructure
- Restoration of civil and structural elements
- Integration with Central Bridge Management system (COB)

### Required services

- Design services for [civil engineering](https://pelenoir.com/en/tenders-of-europe/disciplines/engineering/) works
- [Construction works](https://pelenoir.com/en/tenders-of-europe/disciplines/construction/) for bridges
- Mechanical and electrical engineering
- Structural engineering

## Pelenoir assessment

The project primarily involves the renovation of two movable bascule bridges, with a strong focus on engineering and technical planning for structural, mechanical, electrical, and civil works. The two-phase construction team (bouwteam) process also necessitates project and [construction management](https://pelenoir.com/en/tenders-of-europe/disciplines/project-and-construction-management/) for design coordination and execution, as well as physical construction and general contracting for the realization phase.

## How to take part

### Who can apply

- Participation is not reserved
- Submission via [TenderNed](https://pelenoir.com/en/tenders-of-europe/sources/tenderned/) is required
- Uniform European Procurement Document (UEA) is used for selection criteria
- Minimum and maximum of 5 candidates invited for the second phase

### What to submit

- Submissions must be in Dutch
- Electronic submission is required via TenderNed
- Uniform European Procurement Document (UEA) must be completed
- Reference projects for selection criteria must be provided

### Award criteria

- Price (20% weight)
- Quality (80% weight)

## Tender documents

The visible document package includes the official tender notice in PDF format, detailing the procurement process and legal framework. Functional and technical specifications for the movable bridges are provided in a separate PDF, likely covering design requirements, performance criteria, and integration with the Central Bridge Management system. Selection guidelines and reference project templates are included as both PDF and DOCX files, outlining eligibility, experience requirements, and evaluation criteria for contractors. Contract-related documents, such as the construction team agreement (bouwteamovereenkomst) and general procurement conditions, are also present, along with declarations and compliance forms. A ZIP file labeled 'Impressie' may contain visual materials like drawings, photos, or 3D models of the existing bridges or proposed designs, but its exact contents cannot be confirmed without access.

## Disciplines

- **Engineering** (primary, 60%): Structural, mechanical, electrical, and civil engineering for the renovation of the two movable bascule bridges, including steel deck replacement, mechanical and electrical installations, structural reinforcements, and integration with the Central Bridge Management system (COB).
- **Project and construction management** (secondary, 20%): Management of the two-phase construction team (bouwteam) process, including coordination of the design phase and subsequent realization phase, ensuring compliance with timelines, budgets, and contractual agreements.
- **Construction and contracting** (secondary, 20%): Physical execution of the renovation works, including installation of new steel bridge decks, mechanical and electrical systems, structural reinforcements, and civil repairs during the realization phase.

## Related projects

- [Government office MEP upgrade: gas-free heating and future-proof systems](https://pelenoir.com/en/tenders-of-europe/projects/government-office-mep-upgrade-gas-free-heating-and-future-proof-19318/) — Apeldoorn, Netherlands · Service contract · deadline 2026-12-18 (20 days left to apply)
- [Utrecht Movable Bridges Engineering Services Framework](https://pelenoir.com/en/tenders-of-europe/projects/utrecht-movable-bridges-engineering-services-framework-16034/) — Utrecht, Netherlands · Service contract · deadline 2026-12-02 (4 days left to apply)
- [New emergency outlet at Eindhoven WWTP](https://pelenoir.com/en/tenders-of-europe/projects/new-emergency-outlet-at-eindhoven-wwtp-16162/) — Eindhoven, Netherlands · Service contract · deadline 2026-12-08 (10 days left to apply)
- [Fietsecoduct A13 Delft](https://pelenoir.com/en/tenders-of-europe/projects/fietsecoduct-a13-delft-15065/) — Delft, Netherlands · Service contract · deadline 2027-01-15 (48 days left to apply)
- [Dordrecht Traffic Bridge Dordtse Side Landing](https://pelenoir.com/en/tenders-of-europe/projects/dordrecht-traffic-bridge-dordtse-side-landing-18231/) — Dordrecht, Netherlands · Service contract · deadline 2027-02-11 (75 days left to apply)
- [New WWTP Huizen-Blaricum Engineering Services](https://pelenoir.com/en/tenders-of-europe/projects/new-wwtp-huizen-blaricum-engineering-services-15908/) — Huizen-Blaricum, Netherlands · Service contract · deadline 2027-01-11 (44 days left to apply)

## Source

Original notice on TenderNed: https://www.tenderned.nl/aankondigingen/overzicht/449632  
Original title: Bouwteam renovatie Potters- en Rabatbrug

Summary and assessment prepared by Pelenoir from the public notice. The original notice is binding.

---
HTML version: https://pelenoir.com/en/tenders-of-europe/projects/renovation-of-two-1950s-bascule-bridges-in-gouda-19737/  
All projects as JSON: https://pelenoir.com/en/tenders-of-europe/projects.json