title: "Hungarian High-Voltage Electrical Power System Design Package 1"
url: "https://pelenoir.com/en/tenders-of-europe/projects/hungarian-high-voltage-electrical-power-system-design-package-1-13502/"
id: 13502
country: "Hungary"
client: "E.ON Észak-dunántúli Áramhálózati Zrt."
type: "Service contract"
procedure: "Open procedure (Uniós eljárás)"
deadline: "2026-10-15"
status: "closed"
days_left: -44
status_as_of: "2026-11-28"
disciplines: ["Engineering","Sustainability","Architecture"]
source: "EKR"
source_url: "https://ekr.gov.hu/eljarastar/eljaras/EKR001586602026"
updated: "2026-09-14"
publisher: "Pelenoir – Tenders of Europe"
---

# Hungarian High-Voltage Electrical Power System Design Package 1

> Design services for high-voltage electrical power distribution infrastructure, including substations and transmission lines across multiple regions in [Hungary](https://pelenoir.com/en/tenders-of-europe/countries/hungary/).

**Status (2026-11-28):** Closed 44 days ago — deadline 2026-10-15 14:00  
**Location:** Hungary  
**Contracting authority:** E.ON Észak-dunántúli Áramhálózati Zrt.  
**Opportunity type:** Service contract — Open procedure (Uniós eljárás)  
**CPV:** 71323100; 71320000 Engineering design services  

## About the project

Design services for high-voltage electrical power distribution infrastructure, including substations and transmission lines across multiple regions in Hungary. The project involves detailed [engineering design](https://pelenoir.com/en/tenders-of-europe/disciplines/engineering/) for 110 kV and above substations, transformers, and transmission lines, as well as environmental and safety planning for protected species.

## Scope of work

Design services for high-voltage electrical infrastructure, including substations and transmission lines. The scope covers technical, architectural, telecommunications, and environmental planning, as well as compliance with Hungarian and EU regulations.

### Deliverables

- Technical design documentation for substations and transmission lines
- Draft contracts
- Environmental impact assessments and species protection plans
- Compliance documentation for regulatory approvals

### Required services

- Electrical power systems design services
- Engineering design services
- Architectural and telecommunications design for substations
- Environmental planning and protected species management

## Pelenoir assessment

This project primarily involves engineering and technical planning for high-voltage electrical infrastructure, with secondary components in environmental [sustainability](https://pelenoir.com/en/tenders-of-europe/disciplines/sustainability/) and [architectural design](https://pelenoir.com/en/tenders-of-europe/disciplines/architecture/) for substations. The focus is on delivering detailed technical designs, compliance documentation, and environmental protection measures for substations and transmission lines across multiple regions in Hungary.

## How to take part

### Who can apply

- Enrolment in a relevant professional register (Hungarian or equivalent foreign professional chamber)
- Proven experience in high-voltage substation and transmission line design (minimum 10 million HUF for substations, minimum 5 km for transmission lines)
- Qualified personnel with specific professional certifications (e.g., EN-VI, T, GT, HI-V, V, É)
- Compliance with Hungarian public procurement regulations (Kbt. 65. §, 321/2015. Korm. rendelet)

### What to submit

- Technical and financial proposals
- References for similar completed projects
- Professional qualifications and certifications of key personnel
- Environmental and safety compliance documentation

### Award criteria

- 1. Net contractor fee (including option rights)
- 2. Number of additional designers with specified competencies (0-2)
- 3. Additional professional experience of key personnel (0-36 months beyond minimum requirements)
- 4. Commitment to include environmental protection measures in design documentation (yes/no)
- 5. Commitment to include protected species rescue tasks in design documentation (yes/no, for relevant lots)

## Tender documents

The visible document package includes 28 files, primarily labeled as technical documentation for various parts of the project (e.g., 'Műszaki dokumentáció 1. rész' to '12. rész'). These files likely contain detailed technical specifications, design requirements, and environmental planning guidelines for high-voltage substations and transmission lines. One file, 'Hüllők kétéltűek biztonságos eltávolítása_kiadásra.pdf,' suggests specific environmental protection measures for reptiles and amphibians. The 'Szerződéstervezetek' file likely contains draft contract terms, while 'Közbeszerzési dokumentáció' probably includes procurement forms and submission guidelines. The exact content of each file remains uncertain without access, but the titles indicate a focus on technical, contractual, and regulatory compliance documentation.

## Disciplines

- **Engineering** (primary, 70%): Detailed engineering design for high-voltage substations, transformers, and transmission lines, including structural, electrical, and infrastructure planning for 110 kV and above systems.
- **Sustainability** (secondary, 20%): Environmental impact assessments, species protection planning, and compliance with environmental regulations for high-voltage infrastructure.
- **Architecture** (secondary, 10%): Architectural design for substations, including spatial planning and integration of telecommunications systems within the infrastructure.

## Related projects

- [Water management engineering: large-scale canal and flood control design for INTERREG project](https://pelenoir.com/en/tenders-of-europe/projects/water-management-engineering-large-scale-canal-and-flood-control-20681/) — Győr, Hungary · Service contract · deadline 2027-01-14 (47 days left to apply)
- [Railway bridge technical inspection and expert services](https://pelenoir.com/en/tenders-of-europe/projects/railway-bridge-technical-inspection-and-expert-services-16666/) — Budapest, Hungary · Service contract · deadline 2026-12-03 (5 days left to apply)
- [Road design projects in Komárom-Esztergom County](https://pelenoir.com/en/tenders-of-europe/projects/road-design-projects-in-komarom-esztergom-county-18754/) — Tatabánya, Hungary · Service contract · deadline 2026-12-14 (16 days left to apply)
- [Railway bridge and connecting track design over Hármas-Kőrös river](https://pelenoir.com/en/tenders-of-europe/projects/railway-bridge-and-connecting-track-design-over-harmas-koros-river-19361/) — Gyomaendrőd, Hungary · Service contract · deadline 2026-11-27 (closed 1 day ago)
- [Tram line design: new 1 km track and stops on Budafoki út](https://pelenoir.com/en/tenders-of-europe/projects/tram-line-design-new-1-km-track-and-stops-on-budafoki-ut-19362/) — Budapest, Hungary · Service contract · deadline 2026-12-17 (19 days left to apply)
- [Reconstruction design of Rákos út in Budapest XV district](https://pelenoir.com/en/tenders-of-europe/projects/reconstruction-design-of-rakos-ut-in-budapest-xv-district-17693/) — Budapest, Hungary · Service contract · deadline 2026-12-03 (5 days left to apply)

## Source

Original notice on EKR: https://ekr.gov.hu/eljarastar/eljaras/EKR001586602026  
Original title: Főelosztóhálózati tervezés - 1. csomag

Summary and assessment prepared by Pelenoir from the public notice. The original notice is binding.

---
HTML version: https://pelenoir.com/en/tenders-of-europe/projects/hungarian-high-voltage-electrical-power-system-design-package-1-13502/  
All projects as JSON: https://pelenoir.com/en/tenders-of-europe/projects.json